Tower Semiconductor Ltd. Announces Fourth Quarter and Year 2002 Results
- Fab 2 Partners Agree to Advance Final Payments as part of 2003 financing package
- Company continues to advance Fab 2, plans to increase fab capacity to approximately 10K wafers per month by the beginning of 2004
- Cash Flow from Fab 1 Operations Improves Further
MIGDAL HAEMEK, Israel--(BUSINESS WIRE)--Feb. 24, 2003-- -- Tower Semiconductor Ltd. (NASDAQ: TSEM; TASE: TSEM) today announced results for the year and fourth quarter ended December 31, 2002.
Sales for the fourth quarter of 2002 were $15.6 million (including $4.0 million from a previously announced technology-related agreement for Fab 2), as compared with $16.2 million in the preceding quarter (including $4.0 million from a previously announced technology-related agreement for Fab 2) and as compared with $8.8 million in the fourth quarter of 2001. For the fourth quarter of 2002, the company reported a loss of $13.6 million, or $0.33 per share, including non-capitalized Fab 2 expenses (net) of $10.8 million. This is compared to a loss of $14.5 million, or $0.48 per share, including non-capitalized Fab 2 expenses (net) of $11.7 million, for the third quarter of 2002 and compared with a loss of $9.3 million, or $0.41 per share, including non-capitalized Fab 2 expenses (net) of $4.5 million, for the fourth quarter of 2001.
Sales for the year ended December 31, 2002 were $51.8 million (including $8.1 million from a previously announced technology-related agreement for Fab 2), compared with sales of $52.4 million for the year ended December 31, 2001. For the 12 months ended December 31, 2002, the company reported a loss of $51.4 million, or $1.63 per share, including non-capitalized Fab 2 expenses (net) of $37.0 million, compared with a loss of $38.5 million, or $1.92 per share, including non-capitalized Fab 2 expenses (net) of $14.0 million, for the year ended December 31, 2001.
"During the year 2002 we achieved our goal of bringing Fab 2 online," said Dr. Yoav Nissan-Cohen, co-CEO of Tower. "We are currently providing prototypes to our customers using our 0.18 micron CMOS process, as well as initial samples of products based on our mircoFLASH® technology. During 2003, we plan to increase our installed production capacity in Fab 2 from the current 2,000 wafers per month to approximately 10,000 wafer starts per month by the beginning of 2004."
In addition to the completion of Fab 2's construction, the company continued to enhance its capabilities on other areas. The transfer of 0.18-micron process technology from Toshiba was completed. For 0.13-micron technology, a transfer and development agreement was signed with Motorola, and the project continues to move forward. In the design support area, Tower now offers its customers leading design cores, complete set of standard cell libraries, memory compilers and analog blocks. Also last year, Tower raised approximately $150 million in Fab 2 equity financing. Of that amount, $89 million came from commitments previously made by Tower's wafer and equity partners and $61 million was obtained through the sale of debentures and equity to public and private investors. During 2002, Tower's banks provided $142 million of financing for the project and have further provided an additional $30 million in February of this year. The company was also able to achieve a significant cost reduction in the Fab 2 project, which is now estimated at approximately $100 million below the original plan.
"We expect the momentum of last year's accomplishments, combined with the relentless pursuit of new business opportunities, will help us to achieve even greater success in 2003," commented Dr. Nissan-Cohen. "In January 2003 we hired Harold Blomquist, a very senior and seasoned semiconductor professional as Senior VP for Business Operations of Tower and CEO of Tower-USA. Mr. Blomquist brings to Tower broad experience in semiconductor marketing, sales and business development, and we are confident that his contribution will significantly enhance our future success."
The new facility is currently expected to begin limited volume production in the second quarter of 2003. Although the Fab 2 building, tooling, testing and initial prototyping capability were completed on time and under budget, Tower has adjusted the rate of its Fab 2 ramp to reflect the ongoing softness in the market and world economy.
"We expect production orders to increase during the second half of 2003," added Nissan-Cohen. "Initially, most of these orders will come from our wafer partners, and later from other customers which are currently in initial prototyping phases. We are very encouraged by recent market forecasts which predict a strengthening market in the second half of 2003 and during 2004."
"In 2002 Fab 1 returned to generating positive cash flow," continued Nissan-Cohen. "Among the contributing factors to Fab 1's improved results were rigorous cost reduction efforts and the growth in image sensors products. Beginning in the middle of 2002, Tower utilized its 0.5-micron process technology to manufacture the 14-megapixel CMOS image sensor, which is being used in the new Kodak 35mm professional digital camera, the DCS Pro 14 N Digital SLR. Although we are encouraged by the performance of Fab 1, we currently expect Fab 1 sales to remain flat for the first quarter, with increased sales in the second half of 2003, as orders for new CMOS image sensors products increase and new business is generated"
On the financial side, Tower's major shareholders, have now agreed to advance a substantial portion of the fifth and final Fab 2 milestone payments prior to the contractually committed date. This amendment to the investors' investment agreements is subject to the approval of Tower's shareholders, Tower's banks and other regulatory bodies.
Under the terms of the amended fifth milestone payment agreements, Tower's major shareholders, SanDisk Corporation (Nasdaq:SNDK - News), Alliance Semiconductor (Nasdaq:ALSC - News), Macronix International (Nasdaq:MXICY - News), and the Israel Corporation Technologies (ICTech), will pay $24.2 million in the aggregate following final approval of these arrangements, which the company expects to occur in March 2003. No earlier than August 2003, the partners will pay the remainder of the fifth milestone payment if Tower raises an aggregate of $22 million, which Tower must do before the end of 2003.
For the $24.2 being funded in the coming month, the partners will be issued ordinary shares based on a $2.983 per-share price. For the remainder, the partners will be issued ordinary shares based on the price per share at which Tower raises additional funds. Tower has also agreed to allow its wafer partners to convert up to an aggregate of $13.2 million unutilized wafer credits which they may have as of December 31, 2005 into Tower shares based on the shares market price at that time. If the wafer partners exercise this right and are issued more than 5% in the aggregate of Tower's shares at that time, Tower will then offer all of its other shareholders rights to purchase its shares at the same price per share.
"This agreement reflects the continuous support of our partners and investors' in Fab 2," noted Dr. Nissan-Cohen. "The agreement has been structured to be responsive to the arrangements we are currently negotiating with our banks to defer certain upcoming capacity milestones and obligations that require raising additional financing, and which will significantly improve our immediate cash position. Furthermore, our partners will complete their investments under the Fab 2 investment agreements without Tower needing to raise funds from new wafer partners in 2003 and regardless when we achieve the fifth milestone. This will allow us to raise additional funds in better market conditions."
"It is important to note that our partners' support is expressed not only through their consistency in fulfilling their financial obligations, but also through their willingness to advance payments when necessary, invest an additional $20 million in 2002 above their contractually committed investments and their continuous operational work with our teams on several different production projects for Fab 2."
Tower will host a conference call to discuss these results on Monday, February 24, 2003 at 7:30 a.m. Eastern time / 14:30 Israel time. To participate, call 1-800-915-4836 (U.S. toll-free number) or 1-973-317-5319 (international) and mention ID code: 286732. Callers in Israel are invited to call local 03-925-5910. The conference call also will be webcast live at www.companyboardroom.com and at www.towersemi.com and will be available thereafter on both Web sites for replay for 90 days, starting at 2:00 p.m. Eastern time on the day of the call.
microFLASH® is a registered trademark of Tower Semiconductor Ltd. NROM is a trademark of Saifun Semiconductor Ltd.
About Tower Semiconductor Ltd.
Tower Semiconductor Ltd. is a pure-play independent wafer foundry established in 1993. The company manufactures integrated circuits with geometries ranging from 1.0 to 0.18 microns; it also provides complementary manufacturing services and design support. In addition to digital CMOS process technology, Tower offers advanced non-volatile memory solutions, mixed-signal and CMOS image-sensor technologies. To provide world-class customer service, the company maintains two manufacturing facilities: Fab 1 has process technologies from 1.0 to 0.35 microns and can produce up to 20,000 150mm wafers per month. Fab 2 features 0.18-micron and below process technologies, including foundry-standard technology, and will offer full production capacity of 33,000 200mm wafers per month. The Tower Web site is located at www.towersemi.com.
Safe Harbor
This press release includes forward-looking statements, which are subject to risks and uncertainties. Actual results may vary from those projected or implied by such forward-looking statements. Potential risks and uncertainties include, without limitation, risks and uncertainties associated with (i) obtaining required approvals of the shareholders of the Company and regulatory authorities, to the amendment to the Fab 2 investment agreements, (ii) raising $22 million before the end of 2003, which is a condition to our major shareholders payment of the remaining portion of the fifth milestone, (iii) conditions in the market for foundry manufacturing services and in the market for semiconductor products generally, (iv) obtaining additional business from new and existing customers, (v) obtaining additional financing for the Fab 2 project from wafer partners and/or equity partners and/or other sources, (vi) any failure by Tower to raise additional funding by the deadlines set forth in its agreement with its banks and/or a failure by Tower to reach an agreement with its banks to extend the deadlines to raise additional financing in 2003 and/or failure by Tower to get the approval of its banks to the amendment to the investment agreements, which would result in an event of default of Tower's loan agreement, in which event the banks would have the right to call the loans and exercise its liens against Tower's assets, (vii) a declaration of default by Tower's wafer partners, financial investors and the Investment Center of the State of Israel should Tower's banks call the loans, (viii) satisfaction of all other conditions under the agreements with the Fab 2 equity and wafer partners, the Israeli Investment Center and Tower's banks, (ix) completing the construction of a new wafer manufacturing facility, (x) successful completion of the development and/or transfer of advanced CMOS process technologies to be utilized in Tower's existing facility and in Fab 2, (xi) market acceptance and competitiveness of the products to be manufactured by Tower for customers using these technologies, (xii) ramp-up of production at Fab 2 and (xiii) if we fail to meet certain sales levels and other conditions, we may lose our exclusive foundry license with Saifun.
A more complete discussion of risks and uncertainties that may affect the accuracy of these statements, and Tower's business generally, is included in our most recent Registration Statement on Form F-2, as filed with the Securities and Exchange Commission.
Click here to view the Financial Tables
|
Related News
- Tower Semiconductor Ltd. Announces Fourth Quarter and Year-End 2003 Results
- Tower Semiconductor Reports Fourth Quarter and Fiscal Year 2008 Financial Results
- Tower Semiconductor Ltd. Announces Second Quarter and Six Months 2004 Results; Quarterly Revenues Increased 161 Percent Year-Over-Year and 24 Percent Sequentially
- Lattice Semiconductor Reports Fourth Quarter and Year End Financial Results
- Lattice Semiconductor Reports Fourth Quarter and Year End Financial Results
Breaking News
- Arm loses out in Qualcomm court case, wants a re-trial
- Jury is out in the Arm vs Qualcomm trial
- Ceva Seeks To Exploit Synergies in Portfolio with Nano NPU
- Synopsys Responds to U.K. Competition and Markets Authority's Phase 1 Announcement Regarding Ansys Acquisition
- Alphawave Semi Scales UCIe™ to 64 Gbps Enabling >20 Tbps/mm Bandwidth Density for Die-to-Die Chiplet Connectivity
Most Popular
E-mail This Article | Printer-Friendly Page |