TSMC Details Earthquake Impact, Updates 1Q'16 Guidance
Hsinchu, Taiwan, R.O.C. – February 17, 2016 - TSMC (TWSE: 2330, NYSE: TSM) today updates first quarter 2016 guidance after further examination of the impact of the earthquake that struck southern Taiwan on February 6, 2016. Although there was no structural or serious electric, water, and gases supply damage to the Company’s fabs in Tainan (Fab 6, Fab 14A and Fab 14B), the damage to wafers in progress was greater than our initial assessment announced on the day of the earthquake. In addition, the equipment recovery in Fab 14A, and to a lesser extent Fab 6, would take longer than the initial estimate.
Consequently, TSMC has devoted maximum resources to make up for all the impacted wafers. Nevertheless, we still expect to see wafer delivery delays in the first quarter. More precisely, for Fab 14A, the wafer delivery will be delayed by 10 to 50 days, and delivery of about 100K (12-inch) wafers will be delayed from 1Q to 2Q. For Fab 6, the wafer delivery delay is 5 to 20 days, with 20K (8-inch) wafers delayed to 2Q. For Fab 14B, the delivery delay is negligible. All other fabs located in Hsinchu and Taichung Science Parks are unaffected.
The Company now expects first quarter revenue to be between NT$201 billion to NT$203 billion. Versus the prior guidance provided on January 14, the impact to wafer shipments from the earthquake is more than offset by a combination of business upside and a more favorable exchange rate assumption (USD:NTD of 1:33.18 versus 1:32.50 on January 14).
After factoring in insurance claims, the Company now expects first quarter gross profit margin to be between 44% and 46%. Operating profit margin is expected to be between 33.5% and 35.5%.
In summary, the Company believes all of the earthquake-related costs and expenses have been accounted for in the present first quarter guidance, while we will make every effort and work closely with customers to expedite the delivery of all impacted wafers.
|
Related News
- TSMC Updates 1Q'14 Guidance
- TSMC January 2025 Revenue Report and the Statement on the Impact of Earthquake
- NXP and TSMC to Deliver Industry's First Automotive 16 nm FinFET Embedded MRAM
- Moortec Provide Embedded Monitoring Solutions for Arm's Neoverse N1 System Development Platform on TSMC 7nm Process Technology
- TSMC Details Impact of Computer Virus Incident
Breaking News
- Breker RISC-V SystemVIP Deployed across 15 Commercial RISC-V Projects for Advanced Core and SoC Verification
- Veriest Solutions Strengthens North American Presence at DVCon US 2025
- Intel in advanced talks to sell Altera to Silverlake
- Logic Fruit Technologies to Showcase Innovations at Embedded World Europe 2025
- S2C Teams Up with Arm, Xylon, and ZC Technology to Drive Software-Defined Vehicle Evolution
Most Popular
- Intel in advanced talks to sell Altera to Silverlake
- Arteris Revolutionizes Semiconductor Design with FlexGen - Smart Network-on-Chip IP Delivering Unprecedented Productivity Improvements and Quality of Results
- RaiderChip NPU for LLM at the Edge supports DeepSeek-R1 reasoning models
- YorChip announces Low latency 100G ULTRA Ethernet ready MAC/PCS IP for Edge AI
- AccelerComm® announces 5G NR NTN Physical Layer Solution that delivers over 6Gbps, 128 beams and 4,096 user connections per chipset
![]() |
E-mail This Article | ![]() |
![]() |
Printer-Friendly Page |